Timelines for Sandpit restoration

These indicative timelines for the formative stages of the Kent St Sandpit have been agreed between the Town of Victoria Park and Curtin University. Progress on this project depends on the outcomes of scientific trials and the weather. Timelines may therefore change as the work progresses.

You can download the full restoration plan here. Please note it is a 31-page pdf and should be read on the understanding that things will evolve as the project progresses.

Target dateActivity
2023-24Implement weed control, including chemical control and scalping
Tender construction works for parking, paths, key features
Plant production and seed collection
2024-25Construct paths, key features
Conduct seed and planting trials
2025-26Construct yarning circles, shelter and universal access ramps
If appropriate, prepare seed mixes for direct seeding, mobilise contractors for seeding and planting – mobilisation of contractors may be dependent on when construction of the above construction is complete.
Commence direct seeding and planting of select species – this may be dependent on when construction works is complete. Could potentially commence restoration in controlled stages that will not be impacted by infrastructure works.
Commence direct seeding and planting of select species – this may be dependent on when construction works is complete. Could potentially commence restoration in controlled stages that will not be impacted by infrastructure works.
Commence monitoring seed emergence and survival
Commence focal sites for intense planting
2026-27Remove and dispose of existing bitumen across site. Install DFES access point
Continue weed monitoring and control
Continue (or commence) direct seeding and planting of select species
Continue monitoring seed emergence and survival
Continue focal sites for intense planting
2027-28Complete installation of minor features (e.g. conservation fencing, carpark, signage, drink fountains, bike rack)
Ongoing maintenance and monitoring of infrastructure and restoration
·       Monitoring seedling emergence
·       Selective weed control
Targeting planting of selected species
2028-29Ongoing maintenance and monitoring of infrastructure and restoration